MPS Lead Time Calculation in Odoo



Lead time calculation in Odoo

Lead time calculation in Odoo.

Company security time :


  • Manufacturing : 2 Days,
  • Purchase      : 2 Days,
  • Sales         : 2 Days.

Lead time on Product :


  • Manufacture Lead time : 20 Days (on finish product)
  • Customer Lead Time    : 60 Days
  • Vendor Lead Time      : 5 Days (on component)

Steps :

1) Delivery date on Delivery Order

Create Sales order on 1st March, 2018

Delivery Date : 28/04/2018

Formula :

Order Date + Lead Time = 1/03/2018 + 60 Days = 30/04/2018
                             - Security Time = 2 Days
                                              ============
Delivery Date                                  28/04/2018


2) Manufacture Deadline :

Manufacturing Deadline Start = 06/04/2018

Formula :

Delivery Date - Company Security time - Manufacture lead time = Schedule Date

28/04/2018    - 2 Days                - 20 Days               = 06/04/2018


3) Purchase :

manufacture schedule date - Company security time - Purchase(vendor) lead time = Purchase Order Date

06/04/2018                -     2 Days            -  5 Days                    = 30/03/2018

Schedule Date = Purchase Order Date + Purchase(vendor) lead time
              = 30/03/2018          +  5 Days
              = 04/04/2018